2024-12-14T02:42:48+00:00

LS05 Pipeline Replacement Ice Road

Cruz constructed a 40’ wide, 2.9-mile ice road, from Drill Site L3 to Drill Site L5 along the alignment. This ice road had 6 access ramps in various locations and a 3-acre staging pad. This project was completed ahead of schedule, in almost half the anticipated time, even with several additional scopes added on to the work.

2024-12-13T21:13:50+00:00

Atqasuk Airport Rehabilitation

In 2020, Cruz Construction began the CASC project, barging 23,500 tons of material to Utqiagvik, constructing a 76-mile snow road to Atqasuk, transporting aggregate, and later delivering over 10,000 tons of specialized materials for airport and road projects, culminating in 2023 with resurfacing the Atqasuk airstrip and replacing its lighting.

2024-12-16T23:11:21+00:00

Shageluk Airport Access Road Improvements

Cruz’s Iron Patriot tugboat and Innoko barge initially landed on the bank of the Innoko River, where material was transported to the staging area upriver, approximately 6 miles from the village. At this material site, Cruz produced 9,461 cubic yards of surface course material for the road reconstruction, and barged it daily to the project location.

2024-12-13T05:29:48+00:00

Dalton Highway MP 289-305 Rehabilitation

Cruz performed the rehabilitation and widening of the road, realignments, grade raises, turnout, roadside hardware, and drainage improvements. Cruz developed a new pit for gravel mining, utilizing D10 dozers to push up thawed materials. Over the course of the project, Cruz hauled more than 2,000,000 tons of material, and crushed 400,000 tons of aggregate.

2024-12-13T21:24:09+00:00

Sagavanirktok River Ice Road

Cruz constructed a 1.8-mile ice road and 850-foot-wide ice bridge across the Sagavanirktok River from Drill Site 17 to Worley Yard Ramp, achieving 12-foot ice thickness in key zones and overcoming extreme cold during the 2019-2020 season to complete the project on time and under budget.

2024-12-14T02:52:41+00:00

Pikka STP Civil-Mining Installation

Cruz’s work on the Oliktok STP Dock Expansion including construction of the dock, which entailed two pile driving crews working in sync to drive 3,018 sheet pile in 57 days. We worked with skilled divers to install an underwater outfall line.  Cruz also constructed 3.1 miles of onshore ice road and 17 acres of onshore ice pad, 6.4 miles of offshore ice road and 8.5 acres of offshore ice pad.

2024-12-12T00:43:47+00:00

Kongiganak Airport Improvements

In the summer of 2023, Cruz began barging roughly 80,000 tons of subbase and 1,700 tons of sand from Platinum to a stockpile site located about 2 miles downriver from Kongiganak. The marine fleet was made up of 5 barges and 4 tugs. In the summer of 2024, a similar marine fleet was used to haul 78,800 tons of subbase from Platinum to the stockpile site, as well as 9,700 tons of E1.

2024-12-14T02:47:19+00:00

Milne Point R Pad

In winter 2023, Cruz Construction installed a 21.5-acre gravel pad west of Deadhorse, removing over 312,000 LCY of overburden, mining 290,000 CY of gravel, constructing ice roads for gravel haul traffic, and returning in summer for final compaction.

2020-01-10T04:25:19+00:00

Kensington Mine – Stage III TTF Dam Raise

In 2018 we performed a Dam raise in remote South East Alaska at the Kensington Gold Mine for Coeur. The Dam was designed to have a life expectancy of 200 years, and implemented a concrete spillway with a structural fill of roller compacted concrete (RCC) underneath it. With very limited space, a batch plant was setup for producing the structural concrete spillway and the RCC.

2020-01-10T04:29:51+00:00

Fort Knox – TSF Dam Raise

In 2011 Alaska Aggregate Products was awarded the bid from Kinross Fort Knox to raise their embankment earth dam. This project offered unique challenges, very precise specifications for lift materials, compaction, and density. Of course, these challenges became even greater with summers that had heavy rainfall. Nonetheless, we successfully completed the work required every year until the construction completion in 2017.

2019-12-31T04:14:55+00:00

Tesoro Refinery Turnaround

Provided crane and heavy haul services for Tesoro at their Kenai refinery. They shut their facility to perform large scale maintenance and upgrades to the existing processing units. Cruz had a total of six cranes onsite for support, which included five 65-75 ton rough terrain cranes and one 230 ton lattice crawler.

2019-12-27T03:18:36+00:00

Smith Bay Exploration

In June of 2015 Caelus Energy decided to move forward with a winter exploration program in Smith Bay, Alaska. The primary objective of the 2015 / 2016 exploration program involved drilling two offshore exploration wells to depths near 6,500’ and 9,500’. Smith Bay is approximately 150 miles from Prudhoe Bay and 130 miles from the nearest road.

2024-12-13T05:30:15+00:00

Umiat Exploration

Over two winter seasons, the Umiat Exploration project included the construction of 202 miles of snow Trail, 20 miles of Ice Road, Five 500’x 500’ ice pads, 18 significant ice crossings, operation of three camps with approximate peak capacity of 120 people, 729 round trip all-terrain vehicle loads for a total of 147,500 miles of travel including transport and support of Kuukpik Drill Rig 5.

2024-12-13T05:33:24+00:00

NUNA Development Project

The scope of work required for this project included the mobilization and operation of a 75-bed remote camp, mine site development, construction of three miles of on-shore ice road and 10 miles of offshore ice road to develop the NUNA Gravel Road & Pad for Caelus Energy Alaska.

2024-12-11T22:42:52+00:00

Moose Pad

The Moose Pad project required the expansion of Milne Pit, an existing gravel mine in Kuparuk, to support the construction of a drilling and production gravel pad.

2024-12-13T04:51:28+00:00

Winx #1 Ice Road

In the fall of 2018 Captivate Energy Alaska selected Cruz Construction to construct and maintain a 12 mile ice road in support of their exploration program. Cruz completed the ice road ahead of schedule and continued to provide maintenance support throughout Captivate throughout their 2018/2019 exploration program.

2024-12-13T21:30:49+00:00

Badami Ice Road

Cruz constructed and maintained the 27 mile Ice Road in support of Glacier Oil and Gas’ 2017 Badami B1-Starfish Exploration Drilling program.

2020-01-10T04:39:43+00:00

Anaktuvuk Pass CWAT

Cruz Construction, partnering with the North Slope Borough, is tasked with constructing the Community Winter Access Trail (CWAT) for Anaktuvuk Pass, Alaska. This program was coordinated between Cruz Construction, North Slope Borough, State of Alaska, and the Bureau of Land Management

2019-12-27T02:58:43+00:00

Doyon Totchaket #1 Exploration

Cruz Marine was hired by Doyon in order to support their exploration program by providing full time transport services for personnel, equipment, and supplies. The Totchaket #1, was located near Nenana, yet across the Nenana River, therefore Cruz Marine utilized their shallow draft marine assets to support the project.

2024-12-13T05:15:43+00:00

Caelus Exploration Support

In 2015, Cruz Marine, partnering with Cruz Construction, was selected to provide all marine services for the Smith Bay Exploration program. Cruz Marine provided 6 tugs and 5 barges to transport necessary exploration supplies and equipment from Prudhoe Bay to Point Lonely, Alaska. Following completion of the exploration program, Cruz Marine demobilized supplies and equipment back to Prudhoe.

2024-12-11T23:56:44+00:00

Nuvagapak Environmental Cleanup

Cruz Marine was selected by Marsh Creek to assist with the transport of contaminated material out of the White Alice Nuvagapak cleanup site. This is one of the most challenging areas in Alaska for extracting assets via water due to the extremely shallow depths and extreme tides.

2024-12-13T05:29:27+00:00

Tok Cutoff MP 38-50 Rehabilitation

This CMGC project was awarded to Cruz in December of 2017. Throughout 2018, Cruz partnered with Northern Region AKDOT to help design and complete the construction package through the CMGC process. In April of 2019 Cruz started construction on this 12 mile section of the Tok Cutoff Highway.

2024-12-12T00:39:36+00:00

Kiana Airport Improvements

With no nearby gravel sources, Cruz pioneered and built and 3 mile access road to a nearby mountain where we opened up a 100 acre material site to provide over 700,000 Tons of aggregate for the project. Other elements of the project included drainage improvements, new lighting system, and apron expansion.

2019-12-27T02:43:29+00:00

Road to Tanana

This two year construction project entailed constructing a new 33 mile road that connected the villages of Manley Hot Springs and the village of Tanana. Not only did Cruz construct 33 miles of road, but we also installed a Bulb Tee Bridge and multiple structural plate pipes for drainage. This was the first new road in Alaska in over 50 years.

2020-01-10T04:50:43+00:00

DSP Campground & Visitor Center

This unique project involved clearing 26 acres, 85,000 cubic yards of excavation, 105,000 cubic yards of Borrow, 2 mile of pioneered road, parking lot, 32 campsites, orientation kiosk, and toilet facilities. The primary objective involved construction and opening of a new campground facility for traveling Alaskans and tourists.

2019-12-27T02:40:09+00:00

Fire Island

The purpose of this project was to install two submarine cables 3.2 miles between Anchorage and Fire Island as part of the Fire Island Wind project. The cables were to be installed a minimum of ten feet apart and to a minimum depth of 5 feet.

2024-12-11T23:29:46+00:00

Grayling Airport

The Grayling Airport Improvements project consisted of replacing the existing 2,800 linear foot runway with a new 4,600 linear foot runway in the Yukon River village of Grayling, AK. This work includes construction of the 4,600’ by 150’ runway, the 325’ by 120’ taxiway, the 350’ by 450’ parking apron, the 1150’ by 24’ access road, and the new lighting system.

2024-12-11T23:30:50+00:00

Palmer Airport

The Palmer Municipal Airport Project was a single season runway rehabilitation project in Palmer, Alaska This project included 66,970 cubic yards of excavation, 77,200 tons of borrow, 12,000 tons of leveling course, 14,000 square yards of recycled asphalt material, 32,890 square yards of removal of existing pavement, and 6,320 tons of asphalt concrete.