Client

Alaska Department of Transportation

Date

2019-2020

Cost

$31 Million

About

This CMGC project was awarded to Cruz in December of 2017. Throughout 2018, Cruz partnered with Northern Region AKDOT to help design and complete the construction package through the CMGC process. In April of 2019 Cruz started construction on this 12 mile section of the Tok Cutoff Highway. This project entails over 10,000 LF of culvert installation, 600,000 Tons of Shot Rock Embankment, 535,000 Tons of Borrow, 300,000 CY of Unclassified Excavation, Bridge Rehabilitation, and 130,000 Tons of Aggregate Base Course D-1.