Client

Santos, Ltd.

Date

December, 2023 – April, 2024

Cost

$29,176,518

About

Cruz’s work on the Oliktok STP Dock Expansion including construction of the dock, which entailed two pile driving crews working in sync to drive 3,018 sheet pile in 57 days. We worked with skilled divers to install an underwater outfall line.  Cruz also constructed 3.1 miles of onshore ice road and 17 acres of onshore ice pad, 6.4 miles of offshore ice road and 8.5 acres of offshore ice pad. Drill and shoot efforts produced 207,248 cubic yards of gravel and 169,726 cubic yards of overburden from E-Pit, which was hauled to the project site.