Client

Alaska Department of Transportation

Date

2018-2019

Cost

$19 Million

About

This airport re-alignment project involved re-aligning the existing 3,800 LF RW to 4,200 LF.  With no nearby gravel sources, Cruz pioneered and built and 3 mile access road to a nearby mountain where we opened up a 100 acre material site to provide over 700,000 Tons of aggregate for the project. Other elements of the project included drainage improvements, new lighting system, and apron expansion. This project was originally scheduled for 2.5 years. Cruz was able to capitalize on efficiencies and our winter experience to accelerate the project schedule and finish in 1 year.