Client

Golder Associates, Inc.

Date

June, 2021- September, 2021

Cost

$3,140,235

About

The purpose of this project, located on Latouche Island, was to temporarily divert flow of Copper Creek through a historic channel to circumvent the flow of water around Mine Lake. Our crew performed on-site assembly and installation of 1,500 feet of 20” – 24” HDPE pipe. Cruz also excavated 10 ft. deep trenches along the entire pipe alignment, filled and placed 3,000+ sand bags, and procured and installed an I beam for the bridge portion of the project. Cruz also provided camp facilities which included full amenities and camp maintenance/management.