Client

Great Bear Pantheon

Date

May, 2022- May, 2023

Cost

$4,370,000

About

Cruz Construction’s work on Great Bear Pantheon’s Alkaid #2 Project included construction of a 2.5 acre gravel pad and access roads at approximately mile 397 of the Dalton Highway, including related mining at the MP 395 pit, mobilization of the Nabors 105 from Deadhorse, and rig support for the drilling and fracking operation. Cruz hauled 57,888 cubic yards of gravel for this work, while also providing 24‑hour well support.